<blockquote>Conducted to prove that the system design meets its requirements with a predetermined margin above expected operating conditions, for instance by using elevated environmental conditions for hardware. (INCOSE 2011,128)</blockquote>
予想される運用条件を所定のマージンだけ上回る条件でも、システム設計がその要求を満たすことを証明するために実施される。例えば、ハードウェアに対して引き上げられた環境条件を用いる。 (INCOSE 2011,128)
<blockquote>Proof that the design will survive in its intended environment with margin. The process includes testing and analyzing hardware and software configuration items to prove that the design will survive the anticipated accumulation of acceptance test environments, plus its expected handling, storage, and operational environments plus a specified qualification margin. Qualification testing usually includes temperature, vibration, shock, humidity, software stress testing, and other selected environments. Qualification by similarity may be used if the item in question is sufficiently similar to a qualified item and the planned use is also sufficiently similar so as to not invalidate the previous qualification evidence and decision. (Mooz, Forsberg, Cotterman 2003, 270)</blockquote>
設計が意図された環境にマージンをもって耐えられることの証明。このプロセスには、設計が、受入試験で想定される環境負荷の累積に加え、予想される取扱い、保管、運用環境、さらに指定された認定マージンに耐えることを証明するための、ハードウェア及びソフトウェアの構成品目の試験と分析が含まれる。認定試験には通常、温度、振動、衝撃、湿度、ソフトウェアストレステスト、その他の選択された環境が含まれる。当該品目が認定済みの品目と十分に類似し、計画された用途も、以前の認定の証拠と決定を無効化しない程度に十分類似している場合、類似性による認定を用いることができる。 (Mooz, Forsberg, Cotterman 2003, 270)
(1) INCOSE. 2011. Systems Engineering Handbook, version 3.2.1. INCOSE-TP-2003-002-03.2.1.
(2) Mooz, H., K. Forsberg, K., H. Cotterman. 2003. Communicating Project Management. Hoboken, NJ, USA: John Wiley and Sons.
The term "qualification" is not well understood, and when asked "Where do the qualification limits come from?" people often say "From the specification." It is the systems engineer's responsibility to determine what the qualification margins should be, with concurrance from the project manager and customer, and then put them into the specification. Lack of understanding of the significance of "Qualification" lead to the death of seven astronauts in the Challenger accident. According to testimony presented in the 1986 Rogers Commission Report on the Space Shuttle disaster, the question was asked in the launch commit meeting the night before the flight, "Are the O-Rings qualified to operate between 40º F and 90ºF (+4ºC and 32ºC) or not?" There was no answer. Since the temperature was expected to be (and indeed was) 29ºF (-2ºC) at launch, no further discussion should have been needed and the launch should have been postponed. A rule: Never operate outside the qualified range.
「認定」という用語は十分に理解されておらず、「認定の限界はどこから来るのか」と尋ねると、人々はしばしば「仕様から」と答える。認定マージンがどうあるべきかを判断し、プロジェクトマネージャと顧客の合意を得て、それを仕様に入れることは、システムズエンジニアの責任である。「認定」の意義に対する理解不足は、チャレンジャー号事故における7名の宇宙飛行士の死を招いた。スペースシャトル事故に関する1986年のロジャーズ委員会報告書で提示された証言によれば、飛行前夜の打上げ可否を判断する会議で「Oリングは 40º F から 90ºF(+4ºC から 32ºC)の間で動作するよう認定されているのか、いないのか」という質問がなされた。答えはなかった。打上げ時の気温は 29ºF(-2ºC)になると予想され(実際にそうなった)ため、それ以上の議論は不要だったはずであり、打上げは延期されるべきであった。規則は次のとおりである:認定された範囲の外で運用してはならない。