システム移行

System Transition

表示:

As part of system deployment, on-site installation, check-out, integration, and testing must be carried out to ensure that the system is fit to be deployed into the field and/or put into an operational context. Transfer is the process that bridges the gap between qualification and use; it deals explicitly with the handoff from development to logistics, operations, maintenance, and support.

システム配備の一環として、システムが現場への配備や運用コンテキストへの投入に適した状態にあることを確実にするため、現地での設置、チェックアウト、統合、試験を実施しなければならない。移管(transfer)は、適格性確認と使用との間のギャップを埋めるプロセスであり、開発からロジスティクス(logistics)、運用(operations)、保守(maintenance)、支援への引き渡しを明示的に扱う。

Definition & Purpose

定義と目的

There are many different approaches to transition or deployment, and many different views on what is included within transition. The SEBoK uses the ISO/IEC/IEEE 15288 definition of transition, as seen below (ISO/IEC/IEEE 15288 2015):

移行や配備にはさまざまなアプローチがあり、移行に何が含まれるかについてもさまざまな見解がある。SEBoK では、以下に示す ISO/IEC/IEEE 15288 の移行の定義を用いる(ISO/IEC/IEEE 15288 2015)。

<blockquote>[The transition] process installs a verified system, together with relevant enabling systems, e.g., operating system, support system, operator training system, user training system, as defined in agreements. This process is used at each level in the system structure and in each stage to complete the criteria established for exiting the stage.</blockquote>

[移行] プロセスは、検証済みのシステムを、運用システム、支援システム、運用者訓練システム、利用者訓練システムなどの関連するイネーブリングシステムとともに、合意で定められたとおりに設置する。このプロセスは、システム構造の各レベルおよび各段階において、その段階を終了するために定められた基準を達成するために用いられる。

Thinking in a linear fashion, the system is transitioned into operation and then would be used and maintained in the operational environment. However, there are other views on transition. For example, the NASA Systems Engineering Handbook states that transition can include delivery for end-use as well as delivery of components for integration (NASA 2007). Using this view, transition is the mechanism for moving system components from implementation activities into integration activities. The NASA discussion of transition also implies that transition can include sustainment activities:

線形に捉えれば、システムは運用へ移行され、その後は運用環境で使用・保守されることになる。しかし、移行については別の見解もある。例えば、NASA の Systems Engineering Handbook は、移行には最終使用のための納入だけでなく、統合のためのコンポーネントの納入も含まれ得ると述べている(NASA 2007)。この見解に立てば、移行とは、システムコンポーネントを実装アクティビティから統合アクティビティへ移す仕組みである。NASA による移行の議論は、移行に維持アクティビティが含まれ得ることも示唆している。

<blockquote>The act of delivery or moving of a product from the location where the product has been implemented or integrated, as well as verified and validated, to a customer.</blockquote>

製品が実装または統合され、さらに検証および妥当性確認が行われた場所から、顧客へその製品を納入または移動する行為。

Many systems are deployed using an iterative or evolutionary approach where operationally useful capabilities are developed and deployed incrementally. While these operationally useful capabilities are fully deployed and transitioned into operational use, transition of logistics, maintenance, and support may occur incrementally or be delayed until after the full system capability is delivered.

多くのシステムは、運用上有用な能力を漸進的に開発・配備していく反復型または進化型のアプローチによって配備される。これらの運用上有用な能力は完全に配備され運用使用へ移行される一方で、ロジスティクス、保守、支援の移行は漸進的に行われたり、システム能力全体が納入された後まで遅れたりすることがある。

Process Approaches

プロセスのアプローチ

Just as there are multiple views on the definition of transition and deployment, there are also several ways to divide the activities required for transition. For example, the NASA Systems Engineering Handbook definition of transition states: This act can include packaging, handling, storing, moving, transporting, installing, and sustainment activities (2007). However, the SEBoK includes the topic of sustainment as separate from transition; this is instead covered under the maintenance and logistics topics. The International Council on Systems Engineering (INCOSE) views the transition process as two-step: planning and performance. Though there are several processes for deployment and transition, most generally include the following activities:

移行と配備の定義に複数の見解があるのと同様に、移行に必要なアクティビティの分け方もいくつかある。例えば、NASA Systems Engineering Handbook の移行の定義は、この行為には、包装、取り扱い、保管、移動、輸送、設置、維持のアクティビティが含まれ得ると述べている(2007)。しかし SEBoK では、維持(sustainment) を移行とは別のトピックとし、保守(maintenance)とロジスティクス(logistics)のトピックで扱っている。国際システムズエンジニアリング協議会(International Council on Systems Engineering、INCOSE)は、移行プロセスを計画と実施の2段階からなるものとみなしている。配備と移行のプロセスはいくつか存在するが、一般的には以下のアクティビティを含む。

• Develop a Deployment/Transition Strategy - Planning for transition activities would ideally begin early in the SE life cycle, though it is possible to conduct these activities concurrently with realization activities. Planning should generally include some consideration of the common lower-level activities of installation, checkout, integration, and testing. Such activities are crucial to demonstrate that the system and the interfaces with the operational environment can function as intended and meet the contractual system specifications. For these activities to be effectively managed and efficiently implemented, the criteria, responsibility, and procedures for carrying out these activities should be clearly established and agreed upon during the planning phase.

• 配備/移行戦略の策定(Develop a Deployment/Transition Strategy) - 移行アクティビティの計画(Planning)は、理想的には SE ライフサイクル(life cycle)の早い段階で始めるべきであるが、実現(realization)アクティビティと並行してこれらのアクティビティを行うことも可能である。計画には一般に、設置、チェックアウト、統合、試験といった共通の下位レベルアクティビティへの考慮を含めるべきである。こうしたアクティビティは、システムおよび運用環境とのインタフェースが意図したとおりに機能し、契約上のシステム仕様を満たすことを実証するうえで極めて重要である。これらのアクティビティを効果的に管理し、効率的に実施するためには、その実施に関する基準、責任、手順を計画フェーズのうちに明確に定め、合意しておくべきである。

• Develop Plans for Transitioning Systems - or system capabilities into operational use and support. Transition plans for the system or incremental system capabilities should be consistent with the overall transition strategy and agreed to by relevant stakeholders. Planning for transition will often include establishing a strategy for support, which may include organic support infrastructures, contractor logistics support, or other sources (Bernard et al. 2005, 1-49). It can also include defining the levels of support to be established. The strategy is important because it drives most of the other transition planning activities, as well as product design considerations. Transition plans should include considerations for coordination with the following activities:

• 移行するシステムのための計画の策定(Develop Plans for Transitioning Systems) - システムの能力(capabilities)を運用使用と支援へ移行するための計画である。システムまたは漸進的なシステム能力の移行計画は、全体的な移行戦略と整合し、関連するステークホルダーの合意を得たものであるべきである。移行の計画には支援戦略の確立が含まれることが多く、この戦略には自前の支援インフラ、契約者ロジスティクス支援、その他の供給源が含まれ得る(Bernard et al. 2005, 1-49)。確立すべき支援のレベルを定義することもある。この戦略が重要なのは、他の移行計画アクティビティの大部分に加え、製品設計上の考慮事項をも方向づけるからである。移行計画には、以下のアクティビティとの調整への配慮を含めるべきである。

** Installation - Installation generally refers to the activities required to physically instate the system; this will likely include connecting interfaces to other systems such as electrical, computer, or security systems, and may include software interfaces as well. Installation planning should generally document the complexity of the system, the range of environmental conditions expected in the operational environment, any interface specifications, and human factors requirements such as safety. When real-world conditions require changes in the installation requirements, these should be documented and discussed with the relevant stakeholders. ** Integration - Though system integration activities will generally be performed prior to installation, there may be additional steps for integrating the system into its operational setting. Additionally, if the system is being delivered incrementally, there will likely be integration steps associated with the transition (for more information on integration, please see the System Realization knowledge area (KA)). ** Verification and Validation (V&V) - At this stage, V&V for physical, electrical, and mechanical checks may be performed in order to verify that the system has been appropriately installed. Acceptance tests conducted after delivery may become part of this process (for additional information on V&V, please see the System Realization KA). There are several types of acceptance tests which may be used: ** On-site Acceptance Test (OSAT) - This test includes any field acceptance testing and is performed only after the system has successfully been situated in the operational environment. It may consist of functional tests to demonstrate that the system is functioning and performing properly. *** Field Acceptance Test - This test includes flight and sea acceptance tests; it is performed, if applicable, only after the system has successfully passed the OSAT. The purpose of field testing is to demonstrate that the system meets the performance specifications called for in the system specifications in the actual operating environment. *** Operational Test and Evaluation (OT&E) - An OT&E consists of a test series designed to estimate the operational effectiveness of the system. *** Evaluate the readiness of the system to transition into operations - This is based upon the transition criteria identified in the transition plan. These criteria should support an objective evaluation of the system’s readiness for transition. The integration, verification, and validation activities associated with transition may be used to gauge whether the system meets transition criteria. *** Analyze the results of transition activities throughout and any necessary actions - As a result of analysis, additional transition activities and actions may be required. The analysis may also identify areas for improvement in future transition activities.

- 設置(Installation) - 設置とは一般に、システムを物理的に据え付けるために必要なアクティビティを指す。これには、電気、コンピュータ、セキュリティなどの他システムとのインタフェースの接続が含まれる可能性が高く、ソフトウェアインタフェースも含まれ得る。設置の計画では一般に、システムの複雑さ、運用環境で予想される環境条件の範囲、インタフェース仕様、安全などの人間工学上の要求事項を文書化すべきである。実世界の条件によって設置に関する要求事項の変更が必要になった場合は、その変更を文書化し、関連するステークホルダーと協議すべきである。 - 統合(Integration) - システム統合アクティビティは一般に設置より前に実施されるが、システムを運用の場へ統合するための追加のステップが存在する場合もある。さらに、システムが漸進的に納入される場合には、移行に関連する統合ステップが生じる可能性が高い(統合の詳細については、System Realization 知識領域(KA)を参照)。 - 検証と妥当性確認(Verification and Validation、V&V) - この段階では、システムが適切に設置されたことを検証するため、物理的・電気的・機械的なチェックに関する V&V を実施することがある。納入後に実施される受入試験がこのプロセスの一部となることもある(V&V の詳細については、System Realization KA を参照)。用いられ得る受入試験にはいくつかの種類がある。 - 現地受入試験(On-site Acceptance Test、OSAT) - この試験はあらゆる現場受入試験を含み、システムが運用環境に無事据え付けられた後にのみ実施される。システムが機能し、適切に動作していることを実証するための機能試験で構成されることもある。 - フィールド受入試験(Field Acceptance Test) - この試験は飛行受入試験と海上受入試験を含み、該当する場合には、システムが OSAT に合格した後にのみ実施される。フィールド試験の目的は、実際の動作環境において、システムがシステム仕様で求められる性能仕様を満たすことを実証することである。 - 運用試験・評価(Operational Test and Evaluation、OT&E) - OT&E は、システムの運用有効性を推定するよう設計された一連の試験で構成される。 - システムの運用移行準備状況の評価(Evaluate the readiness of the system to transition into operations) - この評価は、移行計画で特定された移行基準に基づく。これらの基準は、システムの移行準備状況を客観的に評価する助けとなるものであるべきである。移行に関連する統合、検証、妥当性確認のアクティビティを、システムが移行基準を満たしているかどうかを測るために用いることもある。 - 移行活動全体の結果と必要なアクションの分析(Analyze the results of transition activities throughout and any necessary actions) - 分析の結果、追加の移行アクティビティやアクションが必要になることがある。また、分析によって将来の移行アクティビティにおける改善領域が特定されることもある。

Some common issues that require additional considerations and SE activities are the utilization or replacement of legacy systems. It is also common for an organization to continue testing into the early operational phase. The following activities support these circumstances:

追加の考慮と SE アクティビティを要する一般的な課題として、レガシーシステムの利用や置き換えが挙げられる。また、組織が運用初期の段階まで試験を継続することもよくある。以下のアクティビティは、こうした状況を支援するものである。

• System Run-In - After the successful completion of the various acceptance tests, the system(s) will be handed over to the user or designated post-deployment support organization. The tested system(s) may have to be verified for a stated period (called the system run-in, normally for one to two years) for the adequacy of reliability and maintainability (R&M) and integrated logistics support (ILS) deliverables. R&M are vital system operational characteristics having a dominant impact upon the operational effectiveness, the economy of in-service maintenance support, and the life cycle cost (LCC).

• システムランイン(System Run-In) - 各種の受入試験が無事完了すると、システムは利用者、または指定された配備後の支援組織に引き渡される。試験済みのシステムについては、信頼性・保守性(reliability and maintainability、R&M)および統合ロジスティクス支援(integrated logistics support、ILS)の成果物が妥当であるかを、定められた期間(システムランインと呼ばれ、通常は1年から2年)にわたって検証しなければならない場合がある。R&M は、運用有効性、運用中の保守支援の経済性、およびライフサイクルコスト(life cycle cost、LCC)に支配的な影響を及ぼす、極めて重要なシステム運用特性である。

• Phasing-In/Phasing-Out - The need for phasing-in will usually be identified during the system definition, when it is clear that the new system entails the replacement of an existing system(s) (for additional information, please see the System Definition KA). These activities should help to minimize disruption to operations and, at the same time, minimize the adverse effect on operational readiness. It is also important that the phasing-in of a new system and the phasing-out of an existing system occur in parallel with the systems activities of the system run-in to maximize resource utilization. Other aspects of phasing-in/phasing-out to be considered include:

• 段階的導入/段階的廃止(Phasing-In/Phasing-Out) - 段階的導入の必要性は通常、システム定義(system definition)の段階で、新しいシステムが既存システムの置き換えを伴うことが明らかになった時点で特定される(詳細については、System Definition KA を参照)。これらの活動は、運用の中断を最小限に抑えると同時に、運用準備態勢への悪影響も最小限に抑えるのに役立つものであるべきである。資源の利用を最大化するために、新しいシステムの段階的導入と既存システムの段階的廃止を、システムランインにおけるシステムアクティビティと並行して進めることも重要である。段階的導入/段階的廃止に関して考慮すべきその他の側面には、以下のものがある。

** Proper planning for the phasing out of an existing system (if necessary). ** For multi-user or complex systems, phase-by-phase introduction of the system according to levels of command, formation hierarchy, etc. ** Minimum disruption to the current operations of the users. ** Establishment of a feedback system from users on problems encountered in operation, etc. ** Disposal process including handling of hazardous items, cost of disposal, approval etc.

- 既存システムの段階的廃止に向けた適切な計画(必要な場合)。 - 多数の利用者を持つシステムや複雑なシステムの場合、指揮のレベル、フォーメーションの階層などに応じた、段階を追ったシステムの導入。 - 利用者の現行運用の中断の最小化。 - 運用中に遭遇した問題などに関する、利用者からのフィードバックシステムの確立。 - 危険物の取り扱い、廃棄コスト、承認などを含む廃棄プロセス。

Applicable Methods & Tools

適用可能な方法とツール

A system may have to undergo reliability demonstration testing (RDT) to ensure that it meets its contractual R&M guarantees. RDT is conducted under actual field conditions, especially for large systems purchased in small quantity. During RDT, the system is operated in the field within stated test duration and all field data are systematically recorded. At the end of the test period, analysis of the RDT data is performed. Data analysis should facilitate determination of system reliability. One possible output of this analysis is shown in Figure 1 below.

システムは、契約上の R&M 保証を満たしていることを確実にするため、信頼性実証試験(reliability demonstration testing、RDT)を受けなければならない場合がある。RDT は実際の現場条件下で実施され、少量購入される大規模システムではとりわけそうである。RDT の期間中、システムは定められた試験期間内で現場運用され、すべての現場データが体系的に記録される。試験期間が終了した時点で、RDT データの分析を行う。データ分析は、システムの信頼度を判定しやすくするものであるべきである。この分析の出力の一例を下の図1に示す。

図1. 概念的な信頼度分析。(SEBoK Original)
Figure 1. Notional Reliability Analysis. (SEBoK Original)
図1. 概念的な信頼度分析。(SEBoK Original)

図中の英語

System, Subsystem, or Component Reliability
システム、サブシステム、またはコンポーネントの信頼度
Acceptable Minimum
許容可能な最小値
With Mitigation
緩和策あり
Without Mitigation
緩和策なし

References

参考文献

Works Cited

引用文献

Bernard, S., B. Gallagher, R. Bate, H. Wilson. 2005. CMMI® Acquisition Module (CMMI-AM), version 1.1. Pittsburg, PA, USA: Carnegie Mellon University (CMU)/Software Engineering Institute (SEI) CMU/SEI-2005-TR-011.

ISO/IEC/IEEE. 2015.Systems and Software Engineering - System Life Cycle Processes. Geneva, Switzerland: International Organization for Standardization (ISO)/International Electrotechnical Commission (IEC)/Institute of Electrical and Electronics Engineers (IEEE).ISO/IEC/IEEE 15288:2015.

NASA. 2007. Systems Engineering Handbook. Washington, D.C., USA8: National Aeronautics and Space Administration (NASA), NASA/SP-2007-6105.

Primary References

主要参考文献

INCOSE. 2011. INCOSE Systems Engineering Handbook: A Guide for System Life Cycle Processes and Activities. Version 3.2.1. San Diego, CA, USA: International Council on Systems Engineering (INCOSE), INCOSE-TP-2003-002-03.2.1.

ISO/IEC/IEEE. 2015. Systems and Software Engineering - System Life Cycle Processes. Geneva, Switzerland: International Organization for Standardization (ISO)/International Electrotechnical Commission (IEC)/Institute of Electrical and Electronics Engineers (IEEE). ISO/IEC/IEEE 15288:2015.

NASA. 2007. Systems Engineering Handbook. Washington, D.C., USA: National Aeronautics and Space Administration (NASA), NASA/SP-2007-6105.

Additional References

追加参考文献

None.